States in India have tremendous solar and wind energy potential and many developers are putting up such projects in states like Rajasthan, Tamil Nadu and Gujrat.

Following activities are needed to be done and we have out lined ours and developers scope.

1. LABOUR REGISTRATION SCOPE
2 Metering Point SLD Approval Plant End   OURS
3 Meter/CT/PT : Drawing & GTP Approval, Third party testing (NABL Approved Lab),Factory Inspection, Testing and Certification (Plant End & Bay End)   OURS
4 Commissioning Coordination, Metering sealing (M&P,MRT) with EIG/RVPNL/RRECL EIG Electrical Installation Approval for Complete p Plant, Plant End substation &Bay End Substation (In coordination with other vendors)   OURS
6 RT Pre-Commissioning approval from STU/ As requisite authority, etc. (Plant, Bay)   OURS
7 Work Completion letter from Discom/ requisite authority, etc. (Plant &Bay)   OURS
8 Connectivity Report from STU/Discom   OURS
9 SLD Approval   OURS
10 Compliance with terms & Condition of Evacuation of Approval.   OURS
11 Synchronization certificate from STU/Discom   OURS
12 Coordination with various Govt. Department for commissioning   OURS
13 Plant Commissioning   DEVELOPERS
14 District Industries Permission (If required)   DEVELOPERS
15 Construction power connection with Discom (If required)   DEVELOPERS
16 Data Validation with NRLDC   WILL CO ORDINATE WITH SLDC
17 Approval of various drawings from CTU/STU/Discom (Construction, Equipment, Installation)   OURS
18 REGISTRATION WITH RESPECTIVE RENEWABLE ENERGY CORPORATION OF THAT STATE.   DEVELOPERS
19 CONNECTIVITY CHARGES PER MEGA WATT   DEVELOPERS