Renewable Energy
States in India have tremendous solar and wind energy potential and many developers are putting up such projects in states like Rajasthan, Tamil Nadu and Gujrat.
Following activities are needed to be done and we have out lined ours and developers scope.
1. | LABOUR REGISTRATION | SCOPE |
2 | Metering Point SLD Approval Plant End | OURS |
3 | Meter/CT/PT : Drawing & GTP Approval, Third party testing (NABL Approved Lab),Factory Inspection, Testing and Certification (Plant End & Bay End) | OURS |
4 | Commissioning Coordination, Metering sealing (M&P,MRT) with EIG/RVPNL/RRECL EIG Electrical Installation Approval for Complete p Plant, Plant End substation &Bay End Substation (In coordination with other vendors) | OURS |
6 | RT Pre-Commissioning approval from STU/ As requisite authority, etc. (Plant, Bay) | OURS |
7 | Work Completion letter from Discom/ requisite authority, etc. (Plant &Bay) | OURS |
8 | Connectivity Report from STU/Discom | OURS |
9 | SLD Approval | OURS |
10 | Compliance with terms & Condition of Evacuation of Approval. | OURS |
11 | Synchronization certificate from STU/Discom | OURS |
12 | Coordination with various Govt. Department for commissioning | OURS |
13 | Plant Commissioning | DEVELOPERS |
14 | District Industries Permission (If required) | DEVELOPERS |
15 | Construction power connection with Discom (If required) | DEVELOPERS |
16 | Data Validation with NRLDC | WILL CO ORDINATE WITH SLDC |
17 | Approval of various drawings from CTU/STU/Discom (Construction, Equipment, Installation) | OURS |
18 | REGISTRATION WITH RESPECTIVE RENEWABLE ENERGY CORPORATION OF THAT STATE. | DEVELOPERS |
19 | CONNECTIVITY CHARGES PER MEGA WATT | DEVELOPERS |